Commercial Steel Building Extension for Soabar Ltd

Commercial Steel Building Extension for Soabar Ltd

CustomerSoabar Ltd SectorCommercial Printing Building UsageWorkshop / Office LocationWhetstone, Leicester Architect/ProjectMidbrook Design Project Timeline Work commenced: April 2024Groundworks: 6 weeks Steel Building: 1 week for steel frame erection 1 week for roof...
Timber Clad Steel-Framed Building Project in Cheltenham

Timber Clad Steel-Framed Building Project in Cheltenham

CustomerPrivate Client SectorAgricultural Building UsageMachinery Storage/Vehicle Cleaning LocationCheltenham Architect/ProjectMidbrook Design Project Timeline June 2024: On-site work begins Weeks 1-2: Groundworks Weeks 3-5: Construction of steel-framed building Weeks...