With a fast deadline to complete this project in time for the first intake of trainee marine engineers, Midbrook Steel Buildings were recommended to the college to deliver a groundworks & building package within a tight four week programme. With additional resources, the site was cleared and the reinforced concrete raft foundation completed within a week, followed by a tight three week build programme for our insulated building measuring 15m x 30m x 4m to the eaves. Internal works were completed by others, however we ensured that our works were completed to coincide with the remainder of the project programme.